Requirement Coverage in Test Planning Phase of QC ALM


In requirement coverage we have to link each test plan tree with a requirement or requirements in the requirement phase.
By defining requirements coverage for a test, we can track of the relationship between the tests in test  plan and original requirements.

Navigation:
Step 1: Select require test case
Step 2: Go to the “requirement Coverage” menu


Step 3: Click on “Select requirement” tab
Step 4: Double Click on requirement which we want to associate with test case
Step 5: Click on Yes
Repeat the same process to associate all test cases with corresponding requirement.

Analyze Test Plan:
Review Test plan to determine how well it meets the goals that we defined at the beginning of the application management process. Then, analyze test plan by generating reports and graphs

Navigation:
Step 1: Go to “Analyze “ menu
Step 2: Select Report/graphs

Step 3: Click requirement reports/graphs to analyze 